March 2012
Progress continues on the planning and design process to expand the library by 5,000 square feet. The consultant team is responding to comments from the King County Department of Development and Environmental Services (DDES) as part of the pre-submittal process. Meanwhile, design work continues and a second public meeting will soon be set.

February 2012
The planning and schematic design process to expand the Fairwood Library continues. A pre-submittal meeting is scheduled with the project architects and the King County Department of Development & Environmental Services (DDES).

January 2012
The schematic design process continues for the expanded Fairwood Library project. The design team is currently working with the Department of Development & Environmental Services (DDES) to determine if a Conditional Use Permit will be required for the project.

December 2011
The schematic design process continues for the expanded Fairwood Library. The consultant team gathered feedback on the current plans from the community at a public meeting on December 1.

November 2011
Schematic design for the expanded Fairwood Library is well underway. KCLS and its consultant team hosted a public meeting on December 1 at the Fairwood Library to present the current plans and gather feedback from the community.

October 2011
The schematic design process continues for the library expansion project. A public meeting to allow residents to review and offer input on the design will be held on Thursday, Dec. 1, 6:30pm at Fairwood Library.

September 2011
The design phase has begun and KCLS is conducting initial discussions with the project consultants regarding the goals for redevelopment. The plan is to expand the current library by 5,000 square feet to a total of 20,000 square feet. A property survey was recently completed and is being reviewed by the consultant team for permit and design specifications.

August 2011
The design process for the expanded library project began in August, which entailed a property survey, coordination of the consultants and initial discussions about library programs and goals for redevelopment.

July 2011
Progress continues on planning for the expanded Fairwood Library. Schact | Aslani Architects were selected to lead the project design and preliminary design work for the library expansion and renovation is now underway.

June 2011
The planning process continues for the library expansion and renovation project. After receiving bids and interviewing the finalists, Schact | Aslani Architects was selected to lead the expansion and renovation project.

May 2011
The planning process continues for the 5,000 square foot library expansion project. The project bids were due in April and KCLS received submittals from 11 architect and engineering teams. Interviews were scheduled for May 25, 2011.

April 2011
The planning process is underway for the 5,000 square-foot library expansion project. Bids for project consultants were due April 26 and a list of finalists will be selected for interviews.